Soil Test was carried out

Digging of drilling pit

Drilling of pile point

Excavation of 1m and showing of blinding

Pile Integrity Test was carried out

Cracking of bore pile

Iron bending works

Tower Inventory

Riggers erecting the tower at different height

Picture showing 45m Erected

Installation of ladder

Surface preparation

Tower Priming

Riggers painting the tower from top to bottom

Aviation light installed on Tower

Thunder arrestor installed on Tower

Resting platform installed

Schmidt Hammer (Rebound) Test was carried out